Skip to content
Built Heritage· 21 min read·July 15, 2026·Pillar Guide

Heritage Impact Assessment in India: Regulations, Process and Developer Obligations

Heritage Impact Assessment (HIA) is the process of evaluating how a proposed development, project, or change will affect the significance of a heritage site or structure. In India, it operates across an unusually complex regulatory landscape — the AMASR Act, EIA Notification 2006, National Monument Authority permissions, and nineteen separate state heritage Acts — with severe penalties for violations but significant inconsistency in how the requirements are applied in practice.

Quick Answer

Heritage Impact Assessment in India evaluates the effect of proposed development on the cultural significance, physical fabric, and setting of protected heritage sites. The primary legal framework is the Ancient Monuments and Archaeological Sites and Remains Act (AMASR Act, 1958, amended 2010), which prohibits all construction within 100 metres of centrally protected monuments and requires National Monument Authority permission for development in the 100–300 metre regulated area. The EIA Notification 2006 also triggers heritage assessment requirements for specified project categories. Nineteen states have additional heritage protection laws. A properly conducted HIA follows the ICOMOS Guidance on Heritage Impact Assessment (2011) adapted to Indian regulatory context.

A real estate developer in Chennai purchased a plot and began foundation excavation. Midway through piling, the contractor struck a stone-lined well consistent with medieval Tamil construction. Construction was immediately stopped by the Tamil Nadu State Archaeology Department. The site was notified under Section 4 of the AMASR Act. The project — fully planned, financed, and under construction — was halted for two years while the significance of the find was assessed.

This is not an unusual story. Developers, infrastructure agencies, and even government project proponents regularly encounter heritage obligations they did not anticipate — because heritage impact assessment was not conducted, or was conducted poorly, before commitment of resources.

This guide explains what HIA is, when it is legally required versus when it is professional good practice, how to conduct it correctly in the Indian regulatory context, and what it costs — so that heritage encounters become managed decisions rather than project-stopping surprises.

Why Heritage Impact Assessment Matters

Heritage impact assessment is not primarily a box-ticking regulatory exercise. It serves two practical purposes: identifying heritage risks early enough that projects can be designed around them, and providing the evidence base that conservation authorities need to make informed decisions about development proposals.

Projects that skip HIA and encounter heritage during construction face: mandatory stop orders from ASI, state archaeology departments, or courts; project redesign costs that dwarf the original survey budget; potential criminal liability for the developer under AMASR Act Section 30 (punishment up to two years' imprisonment); reputational damage; and significant delay.

Projects that commission proper HIA early in design resolve most of these issues before commitment of construction cost — relocating footprints, adjusting foundation depths, modifying construction methods, or in some cases demonstrating that proposed works do not actually affect heritage significance, allowing the project to proceed with documented permission.

Why this matters: criminal liability

Section 30 of the AMASR Act provides for up to three months' imprisonment and fines for intentional damage to or construction within 100 metres of a centrally protected monument. The Supreme Court has upheld these penalties in multiple cases. Ignorance of monument status is not a defence after the 2010 amendment, which requires all centrally protected monuments to be listed on the National Monument Authority website.

What Heritage Impact Assessment Is

Heritage Impact Assessment (HIA) evaluates the likely effects of a proposed change — a development project, infrastructure scheme, or change of use — on the heritage significance of a place. It is not a heritage survey (which documents what exists), a condition assessment (which records physical state), or an archaeological excavation (which recovers buried evidence). HIA specifically asks: will this proposed change harm what makes this place significant, and if so, how severely?

The ICOMOS Guidance on Heritage Impact Assessments for Cultural World Heritage Properties (2011) provides the internationally recognised methodology framework. While designed for World Heritage Sites, the methodology is applied — with appropriate scaling — to all categories of heritage place in professional practice globally, including Indian heritage sites.

A properly conducted HIA produces: a statement of heritage significance (what makes this place significant and to whom); a description of the proposed change; an assessment of the impacts on each aspect of significance (physical fabric, setting, views, associations, atmosphere); an evaluation of impact magnitude (negligible / minor / moderate / major / catastrophic) and nature (negative / neutral / positive); and a mitigation strategy that minimises negative impacts.

HIA vs Environmental Impact Assessment (EIA)

Heritage Impact Assessment is a specialist component of environmental impact assessment, not a substitute for it. Large projects requiring full EIA under the EIA Notification 2006 should include HIA as a chapter within the full EIA report. For smaller projects near protected heritage without EIA requirement, a standalone HIA is the appropriate deliverable.

The AMASR Act: Prohibited and Regulated Zones

The Ancient Monuments and Archaeological Sites and Remains Act (AMASR Act, 1958, amended by The Ancient Monuments and Archaeological Sites and Remains (Amendment and Validation) Act 2010) is the primary legal instrument for heritage protection in India at the central government level. It covers all centrally protected monuments — those under ASI custody — as well as notified archaeological sites.

The 2010 amendment introduced the National Monument Authority (NMA) and significantly tightened the zone regulations that apply to all centrally protected monuments.

**Prohibited zone (0–100 metres):** All construction is absolutely prohibited. No exception. No permission process. Any structure within this zone built after the monument notification date is an illegal encroachment. Courts have ordered demolition of significant buildings within this zone, including multi-storey commercial buildings in Delhi and Agra.

**Regulated zone (100–300 metres):** Construction is regulated but not prohibited. Any development — including repairs, additions, and reconstruction — requires prior permission from the National Monument Authority. The NMA reviews applications on the basis of heritage impact, visual impact on the monument setting, use compatibility, and compliance with local planning regulations. The NMA may approve, approve with conditions, or reject. This is where HIA is directly required as part of the application.

**Area beyond 300 metres:** No AMASR Act restriction. Local planning authority controls apply. However, projects that will affect the visual setting or atmosphere of the monument from viewpoints within the regulated zone may still be reviewed informally. Large high-rise developments that dominate monument skylines have been challenged in courts even beyond 300 metres.

Datum mismatch in zone measurement

The 100 m and 300 m zones are measured from the notified boundary of the monument, not from the monument structure itself. In some cases, the notified boundary is different from the physical monument footprint — often larger, sometimes poorly demarcated on the ground. Before purchasing land or committing to any design near an ASI site, obtain the official notified boundary survey from ASI and verify it against survey coordinates in WGS84.

EIA Notification 2006 and Heritage

The Environmental Impact Assessment Notification 2006 (MoEF&CC) requires Environmental Impact Assessment for specified project categories above defined thresholds. Heritage impact is required as a component of the baseline study for all Category A and Category B EIA projects that are located near heritage sites.

The EIA Generic Structure and EIA Guidance Documents for various project categories (township development, industrial estates, mining, infrastructure) specify that the baseline environment chapter must include: identification of heritage sites within a defined study area (typically 10 km for large projects, 3 km for smaller), description of their significance and protection status, and assessment of impacts on those sites from the proposed project.

Projects that trigger EIA and are located within AMASR zones require both NMA permission and MoEF clearance — two separate regulatory processes that must be coordinated. The NMA typically requires the EIA chapter on heritage impacts as part of its own review, so the two processes share some documentation.

Heritage impact in EIA is often conducted superficially — listing heritage sites within the study area and stating 'the project will not affect them' without evidence. This is increasingly being challenged by civil society and heritage organisations in environmental hearings. Courts have set aside EIA clearances where heritage impact was not properly assessed.

State Heritage Laws and Committees

Beyond the AMASR Act and EIA Notification, nineteen Indian states have their own heritage protection laws covering monuments not under central ASI protection. These state acts vary significantly in coverage, enforcement vigour, and HIA requirements.

State heritage protection mechanisms relevant to HIA — key states

StatePrimary LegislationRegulatory BodyHeritage CommitteeHIA Practice
Tamil NaduTamil Nadu Ancient and Historical Monuments and Archaeological Sites and Remains Act 1966Tamil Nadu State Department of ArchaeologyState Level Heritage Bureaucratic Authority (SLHBA)Required for development near state monuments; HR&CE has additional controls for active temples
MaharashtraMaharashtra Ancient Monuments and Archaeological Sites and Remains Act 1960; Mumbai Heritage RegulationsState Department of Archaeology; MMRDAHeritage Conservation Committee, Mumbai and PuneHeritage Conservation Committee clearance required for listed structures; HIA increasingly required
RajasthanRajasthan Monuments, Archaeological Sites and Antiquities Act 1961Rajasthan State Department of ArchaeologyState Heritage CommitteeRequired for NMA zone; state protected sites require archaeology dept. clearance
DelhiDelhi Laws Act 1912 applying central acts; local DDA heritage regulationsASI (central); GNCTD Heritage Conservation CommitteeDelhi Urban Arts Commission (DUAC); Heritage Conservation CommitteeSome of India's most active heritage enforcement and HIA requirements
GujaratGujarat Ancient Monuments and Archaeological Sites and Remains Act 1965Gujarat State Department of ArchaeologyGujarat Heritage Conservation CommitteeRequired near state monuments; private listed structures need clearance for modifications
KarnatakaKarnataka Ancient and Historical Monuments and Archaeological Sites and Remains Act 1961Karnataka Department of Archaeology and MuseumsState Heritage CommitteeRequired near protected sites; Hampi buffer zone has specific development controls

HR&CE-controlled temples in Tamil Nadu

In Tamil Nadu, approximately 36,000 temples under HR&CE jurisdiction have additional layers of heritage regulation. Development affecting temple land, temple views, or the temple's ritual function requires HR&CE and — where the temple is ASI-protected — NMA approval. The HR&CE district collector's office is the first point of contact for any development in proximity to an active HR&CE temple.

The HIA Process: Eight Steps

The following process follows the ICOMOS 2011 guidance adapted for the Indian regulatory context. Steps 1–3 are desk-based and typically take one to three weeks. Steps 4–6 require field work and specialist input. Steps 7–8 are the reporting and consultation phase.

  1. 1Heritage identification: systematically identify all heritage assets within the study area — centrally protected monuments, state protected sites, listed buildings, notified archaeological areas, landscapes with cultural significance. Sources: NMA database, ASI list, state archaeology department registers, INTACH heritage inventories, local development plans.
  2. 2Statement of significance: for each identified heritage asset, prepare a statement of significance — what makes it significant (historical, architectural, archaeological, cultural, associative values) and at what level (national, state, local).
  3. 3Understanding the proposed change: document the proposed development in terms of its physical extent, construction methodology, operational phase, and any induced development effects. Translate these into specific potential impact pathways — vibration, visual intrusion, groundwater change, access restriction.
  4. 4Assessment of impacts: for each potential impact pathway on each heritage asset, assess the magnitude (how much change?) and the significance of impact (does the change affect what is significant?). Use a consistent scale: negligible / minor / moderate / major / catastrophic.
  5. 5Evaluation: determine whether identified impacts are acceptable, unacceptable, or acceptable with mitigation. This is a professional judgment that must be reasoned and defensible, not merely stated.
  6. 6Mitigation design: for each unacceptable or marginally acceptable impact, develop specific mitigation measures — design changes, construction method modifications, monitoring requirements, compensation measures.
  7. 7Reporting: produce the HIA report in the required format for the relevant regulatory authority (NMA format for AMASR zone applications; EIA heritage chapter format for MoEF clearances; state authority format as applicable).
  8. 8Monitoring and management: include a heritage monitoring programme in the report — what will be measured, how often, and what triggers remedial action. This is increasingly required by NMA as a condition of permission.

Impact Assessment Criteria and Methods

Heritage impacts must be assessed across multiple criteria. Focusing only on physical impact to fabric — the most common shortcut — misses the majority of heritage impact pathways.

Heritage impact assessment criteria and assessment methods

Impact CategoryWhat to AssessAssessment MethodCommonly Overlooked
Physical fabric impactDirect damage to historic material from excavation, vibration, flooding, contaminationConstruction method review; vibration propagation analysis; blast radius calculationIndirect vibration from piling 150 m away affecting stone with existing cracks
Setting and visual impactChanges to the character, landmark quality, views to/from the monumentViewshed analysis; photomontages; baseline photograph survey from identified viewpointsNight-time lighting impacts; temporary construction visual impact
Groundwater and hydrological impactChanges to groundwater table affecting buried archaeology or monument foundationsHydrogeological assessment; monitoring boreholesDewatering during construction causing rapid groundwater level change
Access and use impactChanges to physical and social access to the heritage placeAccess route analysis; visitor flow modellingConstruction traffic disrupting ritual access to active religious heritage sites
Acoustic environment impactNoise changes affecting heritage experience, acoustic characterNoise propagation modellingRarely assessed; relevant for heritage landscape and acoustic heritage
Setting associations and atmosphereChanges to the intangible qualities — ambiance, historical associations, spiritual characterExpert assessment; stakeholder consultationFrequently dismissed as subjective; however, courts have upheld significance of setting
Indirect and cumulative impactsCombined effect of this project with past and reasonably foreseeable future developmentsCumulative impact assessment across study areaAlmost universally omitted; significant regulatory gap in Indian EIA practice

Mitigation Hierarchy

The mitigation hierarchy for heritage impact follows the same structure as environmental mitigation: avoid, minimise, mitigate, compensate — in strict preference order. Compensation (offsetting heritage loss with financial contribution to conservation elsewhere) is not an internationally accepted approach for irreplaceable heritage fabric, though it is sometimes applied in practice.

  1. 1**Avoid:** Redesign the project to avoid impact entirely — relocate the building footprint, reroute the infrastructure corridor, reduce the project height. Avoidance is always the preferred solution for significant heritage impacts.
  2. 2**Minimise:** Where complete avoidance is not feasible, reduce the scale or nature of impact — reduce foundation depth, use vibration-isolated construction methods, limit construction hours adjacent to heritage sites.
  3. 3**Mitigate:** Where impacts cannot be minimised further, apply specific measures to reduce harm — heritage monitoring during construction, archaeological watching brief, use of heritage-compatible materials, reversible installations.
  4. 4**Offset:** Where some degree of heritage impact is unavoidable and has been permitted by the regulatory authority, contribute to heritage documentation, conservation, or interpretation of the affected or related heritage as an offset. This is appropriate only for minor, unavoidable impacts — it is not a licence to cause significant damage.
  5. 5**Restore:** After construction, restore disturbed areas, remove temporary structures, and repair incidental damage to the extent physically possible.

Cost and Time Estimates

Heritage Impact Assessment cost and time guide — India, 2026

Project TypeHIA ScopeProfessional Fee (₹)DurationKey Deliverable
Small development in NMA regulated zone (100–300 m)Desktop + walkover + NMA report₹1–₹3 lakh4–8 weeksNMA application with HIA chapter, significance statement, impact matrix
Medium infrastructure project near ASI monumentFull HIA with viewshed analysis and consultation₹3–₹8 lakh8–16 weeksStandalone HIA report, photomontages, mitigation schedule
Large EIA project (Category A or B)HIA as EIA heritage chapter + NMA parallel process₹5–₹20 lakh (HIA component)12–24 weeksEIA heritage chapter, separate NMA HIA report where required
World Heritage or UNESCO buffer zone projectFull ICOMOS-methodology HIA with international review₹20–₹75 lakh6–18 monthsICOMOS-format HIA, UNESCO notification, international peer review
Archaeological watching brief during constructionOngoing site supervision by archaeologist₹50,000–₹3 lakh/monthDuration of groundworksDaily site log, finds record, interim reports, post-excavation report

The cost of not doing HIA

NMA stop orders during construction have delayed projects by 18 months to 5 years in documented cases. Demolition orders for structures built in prohibited zones have resulted in losses of ₹50 lakh to ₹50 crore. The cost of a proper HIA — typically ₹1–₹20 lakh depending on scope — is almost always small relative to construction commitment, and negligible relative to the cost of regulatory non-compliance.

Field Notes from Practice

**The discovery problem during construction:** The most common heritage surprise in Indian construction is encountering buried archaeological material during foundation excavation. Old cities like Madurai, Kanchipuram, Thanjavur, Chennai, and Delhi are built on top of centuries or millennia of prior occupation. Foundation piling in Chennai's historic core routinely encounters structural remains from Portuguese, Nawabi, or pre-British occupation. A pre-construction archaeological watching brief — a qualified archaeologist present during all groundwork — is the standard practice for mitigating this risk in international heritage practice. In India, it is rarely required and rarely commissioned voluntarily. Projects that commission it proactively almost always identify material that would otherwise have been destroyed without record.

**Coordinate datum errors in zone mapping:** Several project proponents have submitted NMA applications with survey drawings in the Everest 1830 datum while the NMA database boundary is referenced to WGS84. The datum offset of 100–200 m in South India means a project may appear to be outside the 100 m prohibited zone on the applicant's drawings but inside it in the NMA's reference system. NMA has rejected applications on this basis, requiring resubmission with corrected coordinates. Always confirm the coordinate system of the notified boundary before any zone boundary calculation.

**The underspecified state monument problem:** State protected monuments are not always clearly demarcated on the ground or precisely listed in state registers. Projects in proximity to old towns, village temples, and pre-colonial rural structures encounter state monument designations that were not visible in any database — because state registers are incomplete, not digitised, or simply unknown to the project team. A thorough heritage identification phase must include direct contact with the State Department of Archaeology, not just database searches.

Common Mistakes Made by Developers

  • Assuming that heritage protection only applies to famous monuments: ASI protects over 3,600 monuments; state governments protect many more; local authority heritage lists include thousands of buildings not on these central lists. 'I didn't know it was protected' is not a legal defence after the AMASR 2010 amendment.
  • Measuring zone distances from the monument structure rather than from the notified boundary: the notified boundary is often larger than the monument footprint, particularly for sites with associated features, gardens, or buffer areas. Always obtain the official notified boundary plan.
  • Using WGS84 survey coordinates without converting the official Everest 1830 heritage boundary: produces zone calculation errors of 100–200 m in South India, potentially placing projects in the prohibited zone without realisation.
  • Treating NMA permission as a formality that can be obtained post-construction: NMA stop orders and demolition orders apply to structures built without prior permission in the regulated zone, regardless of construction stage. NMA permission must be obtained before any construction begins.
  • Commissioning an HIA that merely lists nearby heritage assets without assessing impacts: an HIA that states 'there is an ASI monument 250 m from the site; the project will not significantly affect it' with no supporting analysis is not an HIA — it is a heritage inventory. Regulatory authorities and courts are increasingly rejecting such reports.
  • Not addressing visual impact from heritage viewpoints: the setting of a heritage site is part of its significance. A high-rise building that dominates the skyline behind a historic fort or temple affects heritage significance even if it is outside the regulated zone. Setting impact is a legitimate NMA consideration.
  • Failing to commission an archaeological watching brief during groundwork in historically sensitive areas: in areas with known historic occupation, groundwork without archaeological supervision destroys evidence that could have been recorded. This is good practice regardless of whether it is mandated.

Frequently Overlooked Considerations

  • The World Heritage Outstanding Universal Value (OUV) risk: for properties on or near the UNESCO World Heritage List (Hampi, Mahabalipuram, Chola temples, Qutb complex, etc.) and their buffer zones, any development must not affect OUV. UNESCO's Reactive Monitoring procedure can result in placement on the List of World Heritage in Danger — with significant national reputational and tourism consequences.
  • Intangible heritage: active religious sites, festival routes, pilgrimage circuits, and cultural landscapes have intangible significance beyond their physical fabric. A road widening that cuts across a temple car festival route affects cultural significance in ways that physical impact assessment methods do not capture. Stakeholder consultation — with the temple management, community groups, and cultural associations — is the appropriate method.
  • Induced development effects: a single project may be acceptable, but if it catalyses further development in the heritage setting (infrastructure investment triggers surrounding construction), the cumulative impact may be unacceptable. Cumulative impact assessment is technically required by EIA Notification but rarely conducted rigorously.
  • Temporary construction impacts: construction traffic, site hoardings, dust, noise, and vibration during construction affect heritage condition and visitor experience even if the permanent project is heritage-compatible. Construction environmental management plan conditions should address these specifically.
  • Post-permission monitoring: NMA typically requires post-construction monitoring reports confirming that approved heritage mitigation measures were implemented. These reports are often not submitted. Non-compliance with NMA conditions is technically grounds for stop orders on future construction phases.
  • The lender's heritage risk: banks and project finance lenders are increasingly applying international finance institution (IFI) environmental and social standards (IFC Performance Standard 8 on Cultural Heritage) to Indian project loans. These standards require HIA and ongoing heritage management plans as loan conditions — independent of Indian regulatory requirements.

Developer Pre-Application Checklist

  1. 1Identify all ASI centrally protected monuments using the NMA database (nmaindiamonuments.gov.in); plot the 100 m and 300 m zones accurately in WGS84 coordinates and compare against the project site in the same coordinate system
  2. 2Identify all state-protected heritage sites by contacting the State Department of Archaeology directly — do not rely on database searches alone for completeness
  3. 3Identify all locally listed heritage structures and precincts in the local authority development plan, conservation guidelines, and heritage committee registers
  4. 4Confirm whether any of the above identifications trigger mandatory NMA or state authority permission requirements before any construction begins
  5. 5Determine whether the project triggers EIA under the EIA Notification 2006 — if yes, heritage must be addressed as a chapter in the EIA
  6. 6Commission a Heritage Impact Assessment at pre-design stage, not after design is committed — early HIA allows design response; late HIA can only document unavoidable impact
  7. 7Ensure the HIA includes: significance statements, impact assessment across all criteria (physical, visual, groundwater, access, setting), mitigation measures, and a post-construction monitoring plan
  8. 8Submit NMA application with HIA before any construction within the 300 m regulated zone — allow 6–12 months for the NMA review process in the project programme
  9. 9Commission an archaeological watching brief during all groundwork in historically sensitive areas
  10. 10Retain HIA documentation and all regulatory approvals on the project file — they may be required for future property transactions, lender due diligence, and regulatory inspections

Key Takeaways

  • 1The AMASR Act prohibits all construction within 100 metres of centrally protected monuments — no exceptions, no permission pathway. Development in the 100–300 m regulated zone requires prior NMA permission.
  • 2Commission Heritage Impact Assessment at pre-design stage, not after design commitment — early HIA allows design to avoid heritage impacts; late HIA can only document unavoidable harm.
  • 3Coordinate datum mismatch (Everest 1830 vs WGS84) creates zone calculation errors of 100–200 m in South India — always verify zone measurements in a consistent coordinate system against the official notified boundary.
  • 4NMA permission review takes 6–18 months in practice — programme accordingly; construction that begins without NMA clearance in the regulated zone is subject to stop orders and demolition.
  • 5Heritage impact assessment must cover all impact pathways — physical fabric, visual setting, groundwater, access, and intangible values — not just direct physical contact with the monument.
  • 6An archaeological watching brief during groundwork in historically sensitive areas is international standard practice and prevents the most common heritage encounter scenario: undocumented destruction of buried material during construction.

Frequently Asked Questions

What is the prohibited zone under the AMASR Act and what can be done within it?

The AMASR Act defines a prohibited zone of 100 metres measured from the notified boundary of any centrally protected monument. Within this zone, no construction of any kind is permitted — there are no exceptions and no permission process. Existing structures within this zone that predate the monument's notification may be permitted to continue in use but cannot be modified or extended. Courts have ordered demolition of illegal structures within this zone, including multi-storey commercial buildings.

How long does it take to get NMA permission for development in the regulated zone?

The National Monument Authority has a statutory timeline for reviewing applications, but in practice, NMA review takes 6–18 months depending on the complexity of the project, the quality of the application (incomplete applications are returned for resubmission, restarting the clock), and current NMA workload. Projects that are time-sensitive should commission HIA and submit NMA applications at the earliest feasible design stage — not after full detailed design commitment.

Is Heritage Impact Assessment legally required for development near privately owned heritage buildings?

Heritage Impact Assessment is legally required only where the relevant legislation explicitly mandates it — typically within AMASR regulated zones, or as part of EIA for notified project categories. For development near privately owned unlisted heritage buildings, there is no general statutory HIA requirement in India. However, if the development requires local authority planning permission and the local authority has a Heritage Conservation Committee, that committee may require heritage assessment as a condition of reviewing the application.

What is the difference between an ASI NOC and NMA permission for development near a protected monument?

Following the 2010 AMASR amendment, the National Monument Authority (NMA) — not ASI directly — is the statutory body that grants or rejects permission for development in the 100–300 m regulated zone. ASI administers the protected monuments and conserves them, but development permission in the regulated zone is an NMA function. However, ASI is consulted by NMA and may issue technical opinions. An NOC from ASI's local circle office does not substitute for NMA permission — both may be needed, and NMA permission is the statutory clearance.

Can a Heritage Impact Assessment justify development that will cause some harm to heritage significance?

Yes, in limited circumstances. An HIA demonstrates whether impacts are acceptable (negligible or minor impacts that do not compromise significance), acceptable with conditions (moderate impacts that can be sufficiently mitigated), or unacceptable (major or catastrophic impacts that cannot be mitigated to an acceptable level). Regulatory authorities can grant permission with mitigation conditions even where some residual negative impact is identified, provided the development need is demonstrated and the impact is not on irreplaceable values. They cannot grant permission where impacts would compromise Outstanding Universal Value of a World Heritage Site.

J

Jabendra Raja

Technical-Commercial Partner, Evergreen Origins

Jabendra Raja leads the Technical-Commercial practice at Evergreen Origins, working on heritage documentation, GIS, drone survey and 3D modelling projects across Tamil Nadu and South India. Evergreen Origins is currently operational at Birdscale Technologies in the drone and spatial technology space.